City of Fond du Lac issued the following announcement on Sept. 10
WIS 23 Expansion – Urban Section
Location/limits: WIS 23 and various intersecting local roads between US 151 and Seven Hills Road
Description of work: This work is part of the WIS 23 4-lane, on-alignment expansion project in Sheboygan and Fond du Lac counties. Construction in the Fond du Lac urban section of the overall project includes the construction of WIS 23 additional lanes. Work also construction of a roundabout at WIS 23 and Wisconsin American Drive, a jug handle interchange with roundabouts at WIS 23 and County K, and a County K bridge structure over WIS 23. At WIS 23 and County UU, a diamond interchange with roundabouts and a bridge over WIS 23 will be constructed. Other work includes grading, drainage culverts and inlets, aggregate base, concrete pavement, and incidentals.
Traffic impacts:
- CTH UU (South of STH 23) – Closed
- CTH UU (North of STH 23) – Closed
- WB shoulder closure Whispering Springs to 7 Hills Road – Closed